- Baseline execution index (DCMA metric # 14)
- Baseline duration exceeds threshold (DCMA metric # 8)
- Critical path length index (DCMA metric # 13)
- Critical path test (DCMA metric # 12; adding threshold does not delay designated finish task)
- Duplicate task names
- Finish-Start relationships (DCMA metric # 4)
- Hard constraints (DCMA metric # 5)
- Inactive tasks
- Invalid forecast date(s) (DCMA metric # 9 Part 1)
- Invalid actual date(s) (DCMA metric # 9 Part 2)
| - Lags bigger than threshold (DCMA metric # 3)
- Leads bigger than threshold (DCMA metric # 2)
- LOE tasks on critical path (Preamble to DCMA Guide)
- LOE, Summary, Milestone not mutually exclusive (Implied by DCMA Guide)
- Manually scheduled tasks
- Milestones with resources
- Missed tasks (lateness exceeds threshold) (DCMA metric # 11)
- More than threshold number of predecessors (Preamble to DCMA Guide)
- More than threshold number of successors (Preamble to DCMA Guide)
- Negative slack exceeds threshold (DCMA metric # 7)
| - No baseline start or finish date (Excluded by most DCMA tests)
- No predecessors (DCMA metric # 1 Part 1)
- No successors (DCMA metric # 1 Part 2)
- No resources (DCMA metric # 10)
- Out of sequence progress (Preamble to DCMA Guide)
- Planning packages before cutoff date (Preamble to DCMA Guide)
- Slack exceeds threshold (DCMA metric # 6)
- Summary tasks with relationships (Preamble to DCMA Guide)
- Summary tasks with resources
- Tasks with redundant predecessors
|